Lanham EDi 860 map POC02=RZ

  • 1.  Lanham EDi 860 map POC02=RZ

    TOP CONTRIBUTOR
    Posted 5 days ago
    Hello Everyone,

    I'm looking for assitance with a Lanham EDI860 map.

    In the POC-02 I have mapped DI and AI (Delete Item and Add Item Values) and it works,

    I have a new situation where RZ (Replace All Values) is being received in the POC-02 and the POC-04 is NOT being used/mapped.  How do I map it so RZ will trigger a replace all values?

    ------------------------------
    Lewis Rosenberg
    IT Manager
    Mars Fishcare
    Chalfont PA
    www.apifishcare.com
    ------------------------------------------------------------------------
    BCUG/NAVUG All-Star
    BCUG/NAVUG Board of Advisors, Chairperson
    BCUG/NAVUG Programming Committee

    Twitter: @RosenbergL
    LinkedIn: https://www.linkedin.com/in/rosenbergl
    ------------------------------------------------------------------------

    NAVUG/D365BC-Community Summit: https://na.usergroupsummit.com/home
    October 6-9, 2020
    Nashville, TN
    ------------------------------
    Academy - Online Interactive Learning from Experts


  • 2.  RE: Lanham EDi 860 map POC02=RZ

    Posted 4 days ago
    Hi Lewis,
     
    In order to account for the "RZ" EDI Code - Replace All Values - you will need to map a Conditional to send the value to the sales line "EDI Code" field for the POC 02. Then map conditionals on the POC 04, POC 05, and POC 11 using the same setup (Cond. Segment = POC, Cond. Element = 02, Cond. Value = RZ). See the attached screenshots for example mapping. I tested this set up in version SE0.61 but if it's not working for you, please send the Lanham EDI version (Go to E.D.I. Setup page >> About EDI….it's the SE0.xx.xx #) you're on and I will help troubleshoot further.
     
    Thank you,
    Margaret


    ------------------------------
    Margaret Mextorf
    EDI Support Specialist
    Lanham Associates/Lanham Services
    ------------------------------

    Academy - Online Interactive Learning from Experts


  • 3.  RE: Lanham EDi 860 map POC02=RZ

    TOP CONTRIBUTOR
    Posted 3 days ago
    Thanks for the reply @Margaret Mextorf.

    I'm on version 60.03 and it doesn't seem to be working.

    The only difference I saw was that I had "AI" and "DI" along with "RZ" set up in the conditionals for POC-02, but I tried it both ways.
    They are also sending the Qty in on POC-03 and not using POC-04, but I used the conditionals you had on PC-04 on element 03 instead.


    ------------------------------
    Lewis Rosenberg
    IT Manager
    Mars Fishcare
    Chalfont PA
    www.apifishcare.com
    ------------------------------------------------------------------------
    BCUG/NAVUG All-Star
    BCUG/NAVUG Board of Advisors, Chairperson
    BCUG/NAVUG Programming Committee

    Twitter: @RosenbergL
    LinkedIn: https://www.linkedin.com/in/rosenbergl
    ------------------------------------------------------------------------

    NAVUG/D365BC-Community Summit: https://na.usergroupsummit.com/home
    October 6-9, 2020
    Nashville, TN
    ------------------------------

    Academy - Online Interactive Learning from Experts


If you've found this thread useful, dive deeper into User Group community content by role