We have found that NAV 2016 creates production orders with due date and refreshes with scheduling backwards. The start and end dates are then populated. The issues we are seeing is that if we re-enter the
same start date, the end date and due date change. If you re-enter the due date in the header, the start date and end date change. This all happens without refreshing. Does anyone know why?